INCREMENTAL CAPACITY – COST SAMPLE FOR TECHNICAL STUDIES

According to Resolution 245/2019/R/GAS of ARERA, Snam Rete Gas publishes on its website, just as an example, some of the non-binding hypotheses relating to the costs of the technical studies that shall be guaranteed by an appropriate guarantee by subjects that presented the requests of incremental capacity. These costs are represented by a matrix depending on:

Infrastructural consistency:

  • Low, if the length of the pipelines to be developed is approximately less than 15 km and if the project does not normally envisage the construction of compression stations;
  • Medium, if the length of the pipelines to be developed is approximately between 15 km and 100 km and if the project does not normally envisage the construction of compression stations;
  • High, if the length of the pipelines to be developed is approximately more than 100 km.
 

Requested capacity:

  • Low, if the requested capacity is indicatively below 5 MScm/d;
  • Medium, if the requested capacity is indicatively between 5 and 15 MScm/d;
  • High, if the requested capacity is over 15 MScm/d.  
 

  

Cost sample for technical studies:
  Incremental Capacity
  Low
< 5 MScm/d
Medium
< 15 MScm/d
High
> 15 MScm/d
Infrastructural Consistency      
Low < 15 km 40 K€ 50 K€ 60 K€
15 km < Medium < 100 km 150 K€ 200K€  250 K€
High > 100 km 400 K€ 600 K€ 1300 K€
 

  

 